by Nikhil Vishram | Sep 23, 2019
Europa Health Care Tower Office Block Office block development comprising of 2 basements Client: Europa Health Care Limited Project Duration: 74 Weeks ← Mihrab Towers Carrefour Supermarket Village Market Nairobi...
by Designer BAA | Sep 23, 2017
Mihrab Towers Construction of high rise office tower with 3 large basements Client – FCB Project Duration: 104 Weeks ← Kileleshwa Road Europa Health Care Tower Office Block...
by Designer BAA | Aug 26, 2017
Kileleshwa Road Sub-contractor to main contractor for drainage, bridges, asphalt works and walkways Client: Kileleshwa Road Project Duration: 110 Weeks ← Jomo Kenyatta International Airport - Road Works Mihrab Towers...
by Designer BAA | Aug 26, 2017
Jomo Kenyatta International Airport - Road Works Resurfacing and construction of Airport aprons for new terminals. Client: Jomo Kenyatta International Airport – Road Works Project Duration: Weeks ← Two Rivers Development - Road Works Kileleshwa Road...
by Designer BAA | Aug 26, 2017
Two Rivers Development Completed project – Laying of DBM and Asphalt Concrete surface course for Limuru Road, Northern Bypass and all internal links. Client: Two Rivers Development Project Duration: 34 Weeks ← Kasarani Stadium - Road Works Jomo Kenyatta...